The key commercial clauses in construction contracts deal with scope of work, changes to scope and resulting impacts on time and cost as a result of these and other commonly occurring events, which provide certainty for the contracting parties by understanding their responsibilities and obligations upfront when these events occur.
Australian Standard (AS) contracts provide a solid starting point to a contractual framework which include these key commercial clauses. These standard form clauses are often amended to address project specific requirements and to update some of the standard clauses now out of date at common law.
This article outlines the key commercial clauses of construction contracts.
Disclaimer: The information below covers key commercial aspects of construction contracts. It is not an exhaustive list. While Australian Standard contracts address these issues, amendments are often necessary. The approach to amendments varies based on project requirements and the balance of commercial risk agreed between the parties.
A construction contract typically identifies all documents comprising the contract and specifies how those documents are interpreted to the extent of inconsistency between them (by order of precedence). Careful consideration should be given to the order of precedence so that the practical effect of inconsistency between contract documents is properly understood and agreed between the parties.
Careful consideration needs to be given to the following:
If the contract lacks clear definitions or order of precedence, this will create uncertainty. The objective of the contract and its terms are to provide for certainty.
The contract should clearly define the contract price and how adjustments to the contract price are calculated. This is usually done through a variation clause, prime cost clause and/or provisional sum clause.
The contract should identify:
Variation clauses should address as a minimum:
Without sufficient details of how variations are directed and the valuation of these adjustments, disputes can arise with changes to scope.
The contract should address whether the contractor is required to provide security for performance of the contract work, the type of security and the conditions of that security. Security may take different forms, including retention money (deductions from progress payments), bank guarantees or bonds or personal guarantees.
The contract terms concerning security should also specify:
The contract should include a payment clause that aligns with the statutory timeframes for claims, responses and due dates for payment in the BIF Act and QBCC Act (in Qld). Aligning with statutory time frames provides certainty for the parties.
Basic elements of the payment clause should address:
If a milestone contract, where the contractor’s entitlement to payment is triggered on completion of work the subject of those milestones - clear definitions as to what constitutes completion of the relevant milestones is important. In the absence of clear descriptions of the work required to complete a subject milestone, disputes may arise.
A detailed description of the scope of work and related prescriptive and performance based requirements ensures the parties understand the nature and extent of the work required to be performed and the standard to which it is required to meet the project objectives.
The contract should clearly outline:
A scope of work that is deficient or does not adequately describe the end objective in terms of standard and performance will lead to dispute over perceived defects, variations and associated impacts on time and cost. A detailed scope with performance requirements and detailed specifications maximises the alignment between the parties expectations and contract obligations.
A construction program ensures that all parties understand the key milestones, critical activities and critical path for the project. The program should outline as a minimum:
The contract should also require regular (typically monthly) reporting, specifying what must be included as part of that regular reporting:
Unplanned delays to the program of works are common in construction. Your contract should include a clear process for revising the program of works, including processes for claiming and assessing adjustments to milestone dates and the date for practical completion (i.e. a mechanism for Extensions of Time (EOTs)) and a mechanism for claiming, assessing and valuing related delay costs.
The contract should address in detail:
LD’s are a common mechanism parties use to agree upfront an estimate of the principal’s or main contractor’s losses for delays to completion of the work, and in particular a delay to the date for practical completion.
The contract should specify:
LDs provide certainty, set expectations for project timelines, and save the time and cost of proving damages for the party suffering the loss as a result of the delay.
Disputes regularly arise on construction projects and contract should set out a clear and detailed dispute resolution process in a dispute clause.
That dispute clause should include:
A structured approach to dispute resolution provides certainty for the contracting parties and improves the prospects of resolution of the dispute at each stage of the process.
Typically, Australian Standard contracts contain a dispute resolution clause that requires amendment because it was held to be void for uncertainty by the Victorian Supreme Court in 2014.
While Australian Standard contracts provide a strong foundation to construction contracting they often require amendment to reflect project-specific needs.
Ensuring clarity of the key commercial clauses outlined above assists to provide certainty to the parties and minimises the prospect for disputes. When disputes do occur, a well considered dispute clause will also maximise the prospects of resolution of that dispute.
Need assistance with your draft contract? Troy Legal can provide fixed price contract reviews to suit your project. Seek legal advice today: contact us online or call (07) 3854 2315.
The key commercial clauses in construction contracts deal with scope of work, changes to scope and resulting impacts on time and cost as a result of these and other commonly occurring events, which provide certainty for the contracting parties by understanding their responsibilities and obligations upfront when these events occur.
Australian Standard (AS) contracts provide a solid starting point to a contractual framework which include these key commercial clauses. These standard form clauses are often amended to address project specific requirements and to update some of the standard clauses now out of date at common law.
This article outlines the key commercial clauses of construction contracts.
Disclaimer: The information below covers key commercial aspects of construction contracts. It is not an exhaustive list. While Australian Standard contracts address these issues, amendments are often necessary. The approach to amendments varies based on project requirements and the balance of commercial risk agreed between the parties.
A construction contract typically identifies all documents comprising the contract and specifies how those documents are interpreted to the extent of inconsistency between them (by order of precedence). Careful consideration should be given to the order of precedence so that the practical effect of inconsistency between contract documents is properly understood and agreed between the parties.
Careful consideration needs to be given to the following:
If the contract lacks clear definitions or order of precedence, this will create uncertainty. The objective of the contract and its terms are to provide for certainty.
The contract should clearly define the contract price and how adjustments to the contract price are calculated. This is usually done through a variation clause, prime cost clause and/or provisional sum clause.
The contract should identify:
Variation clauses should address as a minimum:
Without sufficient details of how variations are directed and the valuation of these adjustments, disputes can arise with changes to scope.
The contract should address whether the contractor is required to provide security for performance of the contract work, the type of security and the conditions of that security. Security may take different forms, including retention money (deductions from progress payments), bank guarantees or bonds or personal guarantees.
The contract terms concerning security should also specify:
The contract should include a payment clause that aligns with the statutory timeframes for claims, responses and due dates for payment in the BIF Act and QBCC Act (in Qld). Aligning with statutory time frames provides certainty for the parties.
Basic elements of the payment clause should address:
If a milestone contract, where the contractor’s entitlement to payment is triggered on completion of work the subject of those milestones - clear definitions as to what constitutes completion of the relevant milestones is important. In the absence of clear descriptions of the work required to complete a subject milestone, disputes may arise.
A detailed description of the scope of work and related prescriptive and performance based requirements ensures the parties understand the nature and extent of the work required to be performed and the standard to which it is required to meet the project objectives.
The contract should clearly outline:
A scope of work that is deficient or does not adequately describe the end objective in terms of standard and performance will lead to dispute over perceived defects, variations and associated impacts on time and cost. A detailed scope with performance requirements and detailed specifications maximises the alignment between the parties expectations and contract obligations.
A construction program ensures that all parties understand the key milestones, critical activities and critical path for the project. The program should outline as a minimum:
The contract should also require regular (typically monthly) reporting, specifying what must be included as part of that regular reporting:
Unplanned delays to the program of works are common in construction. Your contract should include a clear process for revising the program of works, including processes for claiming and assessing adjustments to milestone dates and the date for practical completion (i.e. a mechanism for Extensions of Time (EOTs)) and a mechanism for claiming, assessing and valuing related delay costs.
The contract should address in detail:
LD’s are a common mechanism parties use to agree upfront an estimate of the principal’s or main contractor’s losses for delays to completion of the work, and in particular a delay to the date for practical completion.
The contract should specify:
LDs provide certainty, set expectations for project timelines, and save the time and cost of proving damages for the party suffering the loss as a result of the delay.
Disputes regularly arise on construction projects and contract should set out a clear and detailed dispute resolution process in a dispute clause.
That dispute clause should include:
A structured approach to dispute resolution provides certainty for the contracting parties and improves the prospects of resolution of the dispute at each stage of the process.
Typically, Australian Standard contracts contain a dispute resolution clause that requires amendment because it was held to be void for uncertainty by the Victorian Supreme Court in 2014.
While Australian Standard contracts provide a strong foundation to construction contracting they often require amendment to reflect project-specific needs.
Ensuring clarity of the key commercial clauses outlined above assists to provide certainty to the parties and minimises the prospect for disputes. When disputes do occur, a well considered dispute clause will also maximise the prospects of resolution of that dispute.
Need assistance with your draft contract? Troy Legal can provide fixed price contract reviews to suit your project. Seek legal advice today: contact us online or call (07) 3854 2315.